Boiler Commissioning Functional Testing - Commissioning (Cx) any type of HVAC equipment is many different procedures from the beginning of the commissioning process to the end of the process. One of the most important procedures during the Cx process is functional testing. Functional testing always precedes the final testing where a test of all the combined equipment is done in an integrated systems testing. Once successful testing is completed and all discrepancies corrected a final commissioning report is generated including all the test data and information collected during the entire process of testing and commissioning.
This is simply a basic set of tests to be performed for boiler functional testing. Each system is different and will require a different tailored test based on equipment submittals, control programs, and design documents. The pre-functional checklist should be complete before engaging in this test.
Functional testing of a hot water boiler in the commissioning process can be streamlined if coordinated properly. Much of the Functional Testing Procedure can be accomplished by coordinating with the startup technician or engineer and the test and balance crew. During startup, the boiler start-up technician should test and verify the proper function of the boiler per the manufacturer’s specifications. During and after the startup the technician should generate a report of all startup work done including adjustments, calibrations, and test data collected during the startup. The Cx Technician or Engineer can then verify first-hand essential data needed to complete the Functional Testing Procedure document. The same applies by coordinating with the Test and Balance crew.
After the startup and test and balance is complete and all final reports are received from the startup and test and balance crews then the Cx tech can perform a thorough pre-functional and functional test of the boiler or boiler system. The following are not all-inclusive of every boiler installation. The list should be tailored for each individual installation. Initial checks of the boiler should include:
Outside equipment should be checked for proper insulation
Equipment is clean and free of any physical damage including any debris inside of any control panels.
All safety devices, including the pressure relief valve, have been tested and tagged according to local code and national requirements.
All unit identification tags, piping labels, operating manuals, maintenance checklist, and basic documentation are with the boiler(s).
All pipes have been flushed and strainers cleaned.
If the boilers are controlled by a building automation system (BAS) ensure the BAS system is checked while performing the procedure. All program functions including alarms, program lockouts, and other BAS variables are checked and ready for testing. Temperature sensors need to be verified for proper installation and location according to representative graphics on the display monitor. All setpoints and rest schedules need to be verified including the outside air temperature device calibration. Lockouts and reset schedules in the BAS and otherwise need to be taken into consideration before functional testing. Once all the basics are checked the next step is physical testing as follows:
Start all circulator pumps individually. Check for any noises and for unusual vibrations originating with the pumps individually running and all running at one time. If the pumps are controlled by any variable speed drives ramp pump up to maximum operating speed and back down to minimum speed and check for vibrations and unusual noises.
Check all water loop valve actuation for supply, return, and any bypass valves.
Test pressure loop sensor.
Test all automatic dampers for combustion air, ventilation, and exhaust dampers for proper operation before starting the boiler.
Reset all pumps and valves for normal automatic operation and fire the boiler. For dual fuel systems test both different fuel types. Again check for any unusual vibrations and noises. If the boiler is a modulating boiler run the boiler as the minimum, maximum, and various stages and verify no unusual noises or vibrations.
On shut down after basic testing ensures proper shutdown sequence of the boiler.
Start boiler and shut off the pump. Ensure boiler shuts down based on loss of flow. This should be indicated as an alarm with the BAS. After successful testing is completed restore all settings to normal.
Test the high limit setting on the boiler by lowering the temperature setting on the high limit control. Check that boiler shuts down and that the BAS system indicates an alarm.
Test the low water cut-off by disconnecting the wire to the low water cut-off. Ensure the boiler shuts down and all alarms are indicated at the BAS.
Test any safety controls including safety switches such as temperature limit switches.
Check backflow preventer. Ensure no water is leaking from the device. Most backflow preventers require annual inspections and certification. Ensure the device has been properly inspected and certified. Sometimes, this is done by an outside third-party contractor.
Test valves and actuator functions for valves. Valves not set properly will have a leak rate. Additionally, valves need to be tested when pumps are on at full capacity to ensure valves do seat properly and there is no leakage because of pressure in the system from pump operation.
Primary combustion air factors? Are there dampers that automatically open before boilers fire? If so, are they interlocked to prevent boiler firing if they are closed?
Water treatment system checks
Automatic air vents on risers?
All boiler safeties tested for proper functionality?
Again, this is not all-inclusive of all the checks that need to be performed on all systems as each system has its own unique requirements. This is an attempt to be thorough from the systems I have commissioned previously.
The test is not all-inclusive, the functional test script must be generated and tailored using the mechanical drawings, equipment schedules, project and equipment specifications along with the owner requirements. A successful Boiler Commissioning & Functional Testing procedure will depend on many people including the commissioning team, the owner, the contractors involved, and sometimes the general contractor.
HVAC Tip - You can add energy savings by placing a blanket wrap insulation around your water heaters. Additionally, for electric water heaters, you can have a timer added to the power circuit to turn the water heater off in times when there is no usage. For example: Set the timer to turn the water heater off from 10 p.m. to 4 a.m. Most timers can be customized and set for different times so that the water heater is turned off for most of the day and night. This, along with the insulation (which will keep the water hotter longer), can save in energy usage and your energy costs.
This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Cookie settingsACCEPT
Privacy & Cookies Policy
Privacy Overview
This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.